A Sefton hammer cage in a hurry?

Why was the council hurrying to replace a hammer cage in Litherland Sports Park?

Share
A Sefton hammer cage in a hurry?
The cage in question (Submitted by a reader)

*A version of this article originally appeared in our Sunday newsletter ‘What links an aviary, Wirral’s bins, a Sefton hammer cage and a giant Liverpool mirror?’ on November 15th.


Residents have raised concerns over almost £40,000 spent on replacing a broken hammer cage at Litherland Sports Park.

Several residents had contacted the Monitor, one who said they were ‘mystified’ about why the council was spending so much on something they claimed was so little used.

‘Two thirds of an aviary’ was how one local resident described the cost, referring to Sefton Council’s controversial plan to save £60,000 a year by closing the Botanic Gardens aviary in Southport. The council has since reversed that decision following a legal challenge⁠, although questions remain about the aviary’s future.

Hammer cage, Litherland Sports Park (image: a Monitor reader)

The concerns raised by local residents had prompted us to fire off a Freedom of Information (FOI) request and the response worked its way back to us last week. Among the documents was a contracts waiver form, which the council said also functioned as the business case for the hammer cage spending.

This money had its origins in the very same February budget where the aviary’s fate was buried in a hefty bundle of documents. Here the council approved more than £400,000 for essential works at its leisure facilities, including £37,700 on the hammer cage, or almost 10% of the total.

The need for a replacement was also raised in a cabinet member update to the council’s Adult Social Care and Health Overview and Scrutiny Committee on 24 February. The report explained that a defective support had put the cage out of action and attempts to repair it had failed, leaving replacement as a possible solution at ‘substantial cost’.

We asked the council in our FOI for ‘any requests, proposals or correspondence from athletics clubs or other external organisations concerning the provision or replacement of the throwing cage’. The response was: ‘We do not hold this information.’

The council did tell us the facility had been used by Stanley High School, and Southport and Waterloo Athletic Club, in 2024, though we weren’t told how frequently. Its records showed the cage was out of use throughout 2025 until August 2026.

When we asked how the spending was justified, the council’s FOI response referred us to the waiver, which is where things became even more interesting.

Screenshot from the Sefton Council Contract Waiver (Image: Screenshot)

The waiver sought permission to depart from normal purchasing rules by awarding the contract directly to a supplier rather than doing a full tender. The reason given was the need to get the replacement installed ‘in order to have the cage available for this athletics seasons events’.

According to the business case, the cage was ‘essential’ for hosting the athletics meets. Such equipment wasn’t generally held in stock, but the proposed supplier already had ‘one on order’, potentially shortening the wait.

Two quotes were obtained. Sport & Play Ltd offered to supply and install the cage for £37,700 excluding VAT, with an estimated installation time of six weeks. Athletics Direct quoted £41,000, with an estimated eight-week wait.

The waiver lists the contract period as running from 21 April to 14 August 2026. The council’s FOI response suggests the replacement was available from some point in August, although we haven’t established exactly when it was installed, or whether it was ready for the athletics events cited in the business case.

There’s something else we haven’t yet been able to establish. Sefton confirmed the waiver was granted because Sport & Play could deliver more quickly than other suppliers, but the copy provided to the Monitor has no authorisation date, and the section for the procurement service manager’s review and signature is blank.

Screenshot from the Sefton council contract waiver we received (image: screenshot)

That doesn’t necessarily mean it wasn’t approved. Indeed, the council says it was. But the document doesn’t show when, or by who. It also says the supplier already had a cage on order, raising questions about the timing of the waiver and whether the equipment had already been ordered on the council’s behalf.

We put those questions to Sefton Council but hadn’t received a response by the time of publication.


New to the Mersey Monitor? Welcome! The Monitor is a Merseyside-based and focused public interest news site operating on a not-for-profit basis. All our stories are free to read and we rely on the goodwill of reader donations to keep what we’re doing sustainable and free of any annoying paywalls. Anyone can sign up for free to receive our emails.